Coating repairs on pace for Line 5

Don Horne   

News

Enbridge Inc on Wednesday said coating repairs were under way at its Line 5 oil pipeline in the Straits of Mackinac in Michigan, as exposed metal spots were found during seasonal maintenance that began in May.

“Four locations will require coating repairs where there are bare metal spots ranging from .07 to .43 square feet. The coating repairs are anticipated to take five-to-10 days,” the Canadian pipeline company said on its website.

There were no integrity issues with the Line 5 pipeline and it remains safe, Enbridge added.

Line 5 ships 540,000 barrels per day of light crude oil and propane and is a critical part of Enbridge’s Mainline network, which delivers the bulk of Canadian crude exports to the United States.

Advertisement

(Reuters)